Capital Project 2019

Slider is playing
Jr/Sr High School entrance

February 2025 Update

  • The remaining part of Phase 2b (windows and theatrical) has been awarded, with work scheduled to begin and end in summer 2025.

  • Phase 3 is out to bid

January 2025 Update

Planned work to be completed in summer 2025:

  • Replace windows in the Jr/Sr High School (Phase 2b)

  • Continue lighting work in the Jr/Sr auditorium (Phase 2b)

  • 95% of our parking lots are being milled and paved making them inaccessible (Phase 3)

  • Upgrade bathrooms in the Jr/Sr High School & Elementary School  (Phase 3)

  • Sections of our sidewalks are being replaced making them inaccessible  (Phase 3)

August 2024 Update

  • Phase 2b commenced in summer 2024 – Security Entrances, Jr/Sr High School Auditorium & TV/Radio Studio, Exterior Repairs, Elementary School Offices & Old Library Conversion

  • Windows have been pushed out to Phase 3 bidding

  • Phase 3 will begin summer 2025

September 2023 Update

  • Phase 2a – has been completed (Elementary & Jr/Sr High School Roofs)

  • Phase 1 – Elementary Cafeteria/Elementary Library Conversion (2023)
    (Read more)

  • Completion of Remaining Elementary School Roof (white roof-10%)

  • Phase 2b – Security Entrances/Auditorium/Windows/Exterior Repairs/Elementary Office (2024)

  • Phase 3 – Sitework/Athletic Fields (2025)

August 2023 Update

  • Phase 2a has been completed (Elementary & Jr/Sr High School Roofs)

  • Phase 1 construction is almost done on the new Elementary Cafeteria and the conversion of the old cafeteria to a new library will begin (Read more)

  • Phase 2b will be awarded this school year and will commence summer 2024

  • Phase 3 will begin summer 2025

Why Was This Work Proposed?