Capital Project 2019

February 2025 Update
The remaining part of Phase 2b (windows and theatrical) has been awarded, with work scheduled to begin and end in summer 2025.
Phase 3 is out to bid
January 2025 Update
Planned work to be completed in summer 2025:
Replace windows in the Jr/Sr High School (Phase 2b)
Continue lighting work in the Jr/Sr auditorium (Phase 2b)
95% of our parking lots are being milled and paved making them inaccessible (Phase 3)
Upgrade bathrooms in the Jr/Sr High School & Elementary School (Phase 3)
Sections of our sidewalks are being replaced making them inaccessible (Phase 3)
August 2024 Update
Phase 2b commenced in summer 2024 – Security Entrances, Jr/Sr High School Auditorium & TV/Radio Studio, Exterior Repairs, Elementary School Offices & Old Library Conversion
Windows have been pushed out to Phase 3 bidding
Phase 3 will begin summer 2025
September 2023 Update
Phase 2a – has been completed (Elementary & Jr/Sr High School Roofs)
Phase 1 – Elementary Cafeteria/Elementary Library Conversion (2023)
(Read more)Completion of Remaining Elementary School Roof (white roof-10%)
Phase 2b – Security Entrances/Auditorium/Windows/Exterior Repairs/Elementary Office (2024)
Phase 3 – Sitework/Athletic Fields (2025)
August 2023 Update
Phase 2a has been completed (Elementary & Jr/Sr High School Roofs)
Phase 1 construction is almost done on the new Elementary Cafeteria and the conversion of the old cafeteria to a new library will begin (Read more)
Phase 2b will be awarded this school year and will commence summer 2024
Phase 3 will begin summer 2025